[HN Gopher] Nelson testifies cost-plus contracts have been a "pl...
       ___________________________________________________________________
        
       Nelson testifies cost-plus contracts have been a "plague" on NASA
        
       Author : aml183
       Score  : 113 points
       Date   : 2022-05-04 17:06 UTC (5 hours ago)
        
 (HTM) web link (payloadspace.com)
 (TXT) w3m dump (payloadspace.com)
        
       | mulmen wrote:
       | What happens when a fixed-price project hits a delay? Presumably
       | the bidder eats the loss at first but what happens when they run
       | out of appetite? Does the project just... end?
        
         | vkou wrote:
         | > Presumably the bidder eats the loss at first but what happens
         | when they run out of appetite? Does the project just... end?
         | 
         | That's why these contracts go to large companies, as opposed to
         | small ones.
         | 
         | If a small company loses interest in finishing a fixed-cost
         | project, they might go bankrupt, and leave the government up
         | crap creek without a paddle.
         | 
         | If a big company loses interest, they'll keep struggling along,
         | because they can get hit with the stick of 'you'll never get
         | another contract from us ever again.'
        
         | uberman wrote:
         | Yes, the project just ends and it will end sooner than expected
         | under fixed bidding as the government will almost certainly
         | demand non-contracted changes mid-project that in my experience
         | can have dramatic costs.
         | 
         | Most government projects are structured and paid for in phases
         | and there is no assurance that phase 2 starts at the end of
         | phase 1. No approval to proceed means the project just "ends
         | when it ends".
        
         | stonemetal12 wrote:
         | They get a bad CPAR (Contractor Performance Assessment Rating)
         | and are banned from government contracting in the future.
        
         | bryanlarsen wrote:
         | Yes. https://spaceflightnow.com/2020/01/22/boeing-withdraws-
         | from-...
        
           | badwolf wrote:
           | More current fixed-price example, also from boeing:
           | https://www.cnbc.com/2022/04/27/boeing-lost-billion-
           | dollars-...
        
         | timdiggerm wrote:
         | You mean if they don't deliver the product after they signed a
         | contract?
        
         | quxpar wrote:
         | Yes, and the government learns a lesson.
        
         | smnrchrds wrote:
         | I don't know what would happen initially, but eventually, the
         | contractors wise up and start baking the risk of delays into
         | their quotes.
        
           | dr_orpheus wrote:
           | Yes, this definitely happens and is why in some situations
           | people think fixed price contracts can end up costing more.
           | 
           | Contractors will be extreme sticklers about their
           | requirements on a project. So that if anything starts look
           | off-plan or may impact something like a schedule delay they
           | will say "nope, that's outside of our scope of work we need
           | an extension/additional funding".
        
             | Goronmon wrote:
             | _Contractors will be extreme sticklers about their
             | requirements on a project. So that if anything starts look
             | off-plan or may impact something like a schedule delay they
             | will say "nope, that's outside of our scope of work we need
             | an extension/additional funding". _
             | 
             | Yup, change orders are how deal with these issues when it
             | comes to fixed-costs contacts. For better or worse, its
             | almost impossible for a project to be perfectly specced out
             | ahead of time. And anything that even comes close to
             | looking like it conflicts with the spec becomes a change
             | order.
        
               | sidewndr46 wrote:
               | According to the article, this is how money is made on
               | cost-plus contracts
               | 
               | > About that "plague": NASA has traditionally procured
               | technology from industry using cost-plus contracts, which
               | allow contractors to charge the agency extra for
               | extensions and changes to their plans.
               | 
               | From my experience, the author of that article has no
               | idea what they are talking about.
        
         | dr_orpheus wrote:
         | Theoretically the bidder eats the loss and assumes all of the
         | risk in a fixed-price contract. Ending projects certainly is a
         | possibility, but there are typically termination penalties
         | within the contracts as well.
         | 
         | If there is an unanticipated issue contractors will often try
         | and get a contract modification because they consider it new
         | scope of work or something like that.
        
         | golem14 wrote:
         | Here's how simple me thinks about it: Cost-plus is just a lazy
         | version of fixed price, where instead of accountants looking at
         | details before new funding is released, there's automatic
         | approval of overruns.
        
           | teruakohatu wrote:
           | > there's automatic approval of overruns.
           | 
           | That is not quite correct. Cost-plus specifies how charges
           | are priced, it does not specify budgets.
           | 
           | I could sell you pencils at cost-plus. How many pencils you
           | buy is up to you, not I.
        
         | fergbrain wrote:
         | They eat the cost: https://simpleflying.com/boeing-ceo-air-
         | force-1-deal-mistake...
        
       | swarnie wrote:
       | Cost plus is a fantastic way top do business.
       | 
       | While working on a cost plus contract in the early 2010s i cant
       | begin to describe the amount of cool shit i bought with a one
       | line explanation as to its purpose.
       | 
       | Probably isn't as cool if the taxpayer is pick up the bill
       | mind....
        
       | Manuel_D wrote:
       | Cost plus contracts are well intentioned, but create perverse
       | incentives. It's also a big issue in the defense industry. The
       | idea is that a contract pays a company the cost of producing a
       | product, plus N% for profit. Thus, profit is fixed and companies
       | cant profit _too_ much off public money.
       | 
       | But in practice, this means that in order to increase profit
       | companies have to increase costs. If you're building a product
       | and you can spend $10 million to build it efficiently or $20
       | million to build it inefficiently, it's actually beneficial to do
       | the latter. It's disincentivizing cost reductions and
       | incentivizing cost increases.
        
         | nynx wrote:
         | There must be some way to structure contracts to allow for cost
         | of developing new technologies yet incentivizes minimizing that
         | cost.
        
           | BurningFrog wrote:
           | One simple way is to pay a fixed sum as profit, not a
           | percentage of costs.
        
           | chmod775 wrote:
           | > There must be some way to structure contracts to allow for
           | cost of developing new technologies
           | 
           | Make companies evaluate and eat the risk by allowing them to
           | set the fixed price...
           | 
           | > yet incentivizes minimizing that cost.
           | 
           | ... where they are bidding on the contract against other
           | companies.
           | 
           | This only works if you have a market with multiple players,
           | which is possibly the main reason NASA is more heavily
           | leaning towards fixed-price contracts now.
        
           | bluGill wrote:
           | R&D is about managing risk. You can have more micro-managers
           | to ensure that costs are minimized, but the cost of all that
           | management can be more than the abuse of cost-plus (not to
           | mention people hate being micro-manged)
           | 
           | The only good answer I've heard is for the agency to have
           | enough technical experts that they can spot bad things.
           | However that means the government needs to develop technical
           | experts.
        
             | kitsunesoba wrote:
             | > The only good answer I've heard is for the agency to have
             | enough technical experts that they can spot bad things.
             | However that means the government needs to develop
             | technical experts.
             | 
             | It's probably beneficial for the contracted company to have
             | technically inclined individuals in leadership too, ranging
             | all the way from the lowest levels up through CEO.
             | Engineering-minded management is much more likely to spot
             | potential troublemakers and risks for runaway costs in the
             | planning phases where someone with a background in
             | management or finance is more likely to fudge things and
             | say "yes we can do this at X unrealistic low cost" just to
             | win a bid. They're also less likely to make bad calls on
             | how to fix budget problems that crop up midway through the
             | contract.
        
           | dr_orpheus wrote:
           | There are Fixed Price Incentive (FPI) contracts that try to
           | address this. Instead of a single price for the contract as
           | in an Firm Fixed Price (FFP) there is a "target" price at
           | which the contractor will get some level of profit. Above
           | that you set a cap on the total cost of a project that you
           | are willing to pay, but the profit of the company goes down
           | as you approach the cost cap. So contractors still have the
           | incentive to minimize cost because if they get cost below the
           | "target" price the contractor still gets that as profit.
           | 
           | However, people aren't usually a fan of them because it
           | requires all of the overhead/audits of a cost-plus contract
           | which typically minimizes how cost effective they can
           | actually be at getting below the target price.
           | 
           | There are also some development-type projects where the
           | government will fund a project, but still require some amount
           | of funds (like 25%) to come from the contractor. But this is
           | really early development type stuff. Basically it is a way to
           | influence where a company is spending their R&D money. Its
           | not really for any operational systems.
        
           | Manuel_D wrote:
           | Ditch cost plus contracts and use taxes to curb companies
           | that are just profiting off rent-seeking behavior (like
           | sitting on patents). This was done during WWII, marginal tax
           | rates were set to 100% to discourage war profiteering.
           | Companies would still have an incentive to cut costs, to
           | increase profits. But they'd then be incentivized to reinvest
           | those profits because otherwise those profits would be
           | greatly taxed. Granted, how you'd effectively target these
           | taxes outside of unusual circumstances like a world war might
           | be too complicated to be feasible.
        
             | treeman79 wrote:
             | This is also the source of the weird health insurance is
             | provided by companies came from. Paying for peoples medical
             | care became an alternative way to compensate people more to
             | avoid absurd taxes. Medical care used to be a lot cheaper
             | so it wasn't a big expense.
        
         | treeman79 wrote:
         | This is also where free markets shine. If someone is making
         | absurd profits building in-efficient widgets. It won't be that
         | long before other people get the idea to make that same widget
         | for less or better quality or both.
         | 
         | But first company will then go out of business or become
         | efficient.
         | 
         | Survival of the fittest evolution style for business.
        
           | WheatM wrote:
        
           | x86_64Ubuntu wrote:
           | This assumes that there are no intellectual property
           | encumberances held by the old company, and that the barrier
           | to entry isn't terribly high. And no one with a budget and a
           | deadline is going to wait for one company to go out of
           | business so they can get it cheaper.
        
           | ipaddr wrote:
           | The first company has first movers advantage which lets them
           | signs exclusive deals and builds a regulatory moat plus gains
           | brand awareness.
           | 
           | The new company may be cheaper or have better quality but
           | that isn't an automatic win. The second company needs more
           | money or an event to superseed the first story.
        
         | fatbird wrote:
         | You're leaving out a significant factor in cost-plus contracts
         | in their favour: the buyer pays the actual cost, not the cost-
         | plus-contingency that's built into fixed price contracts. It
         | may not work out that way for the reasons you mention, but the
         | problem of baking in risk costs to fixed priced bids returns.
         | And in observing "how does the contractor increase profits",
         | another issue with fixed price bids is that it encourages
         | corner-cutting internally: anywhere the contractor can save
         | money, it goes into their pocket, which can mean a lot of
         | tissue-thin requirements fulfillment that goes wrong later.
        
         | Symmetry wrote:
         | In theory the regulating agency overseeing the cost plus
         | contract is supposed to scrutinize the expenses of the overseen
         | entity to prevent this. In practice just form a matter of
         | program complexity this is hard to do. When you bring in
         | politics it gets even worse, "You don't want to endanger our
         | pilots by giving them any less than the most gold plated
         | fighter jets, do you?" argue the defense lobbyists.
         | 
         | The worst example I can think of would probably be the nuclear
         | industry where operators providing grid power on cost plus
         | contracts teamed up with environmentalists after Three Mile
         | Island to get laws passed insisting that nuclear power had to
         | be as safe as possible regardless of cost, which turned into
         | essentially a license to print money.
        
           | ClumsyPilot wrote:
           | > In theory the regulating agency overseeing the cost plus
           | contract is supposed to scrutinize the expenses of the
           | overseen entity to prevent this
           | 
           | The entire point of getting the private sector is that their
           | insentive should be to do it in the most efficient manner
           | possible, and noone has to manage them - the inefficient ones
           | just die out.
           | 
           | The second-best approach is to have the government manage the
           | whole thing, where they have no real incentive to be
           | efficient.
           | 
           | But what we have here is employing the private sector and
           | incentivising them to be as inefficient as possible, and the
           | government must still hire an army of accountants and experts
           | to keep them in check. it's combines the worst aspects of
           | both!
        
             | krapht wrote:
             | For what it's worth, while on any single contract you might
             | get bad behavior from a contractor, their reputation will
             | matter when they go for a recompete or bid on a new
             | contract vehicle.
             | 
             | Not all contracts are automatically won by the lowest-cost
             | bidder. Yes, it allows corruption on the part of the person
             | doing the hiring, but it's better than the alternative.
        
               | astrange wrote:
               | In California, Tutor Perini seems to be famous for
               | winning government construction contracts despite
               | constant failures and unexpected price increases, because
               | the law does require lowest bidder and doesn't allow
               | ignoring low bids from known liars.
        
             | themitigating wrote:
             | The government would have no reason to rip itself off as
             | well unless there's corruption but that should be
             | investigated.
        
               | krapht wrote:
               | You must be somebody who's never had to remove an
               | underperforming colleague on a public project.
               | 
               | What happens is that they get promoted to another team,
               | or put on a project that has absolutely no future, and
               | everyone knows it.
               | 
               | Why is it difficult to remove people? Because in the old
               | days, newly elected executives would clear out the civil
               | service and hire or contract with people that supported
               | their election campaign.
        
               | abathur wrote:
               | They wouldn't have a reason rip themselves off, but the
               | decision-makers may not be well-incentivized to control
               | cost (or might be incentivized to make "safe" choices
               | over "smart" ones).
               | 
               | I have wondered if we could ~endow government agencies in
               | a way that would let them fail, and do the same to spin
               | up ~internal competitors when we feel like turning up
               | competition/innovation.
               | 
               | But it's not something I have gamed out enough steps to
               | feel confident about...
        
         | colordrops wrote:
         | > Cost plus contracts are well intentioned
         | 
         | Are they though? If a casual layman internet reader can see the
         | problem and see that they always get taken advantage of for
         | profit, couldn't also the NASA officials and contractors
         | signing these contracts? They know exactly what they are doing.
         | 
         | SpaceX signed non-cost plus contracts and delivered far more
         | quickly and cheaply than the rest.
        
           | travisporter wrote:
           | The problem is Congress tells NASA do this with this money
           | this way. NASA has little flexibility. Recently with the CLPS
           | program NASA flexed it's muscle and it's paying off so far.
        
         | lumost wrote:
         | In R&D, incentivizing a private enterprise to spend _more_
         | could be beneficial. Assuming the client (NASA) has some
         | oversight this leads to more engineering freedom and an
         | exploration of a larger design space, whereas fixed cost would
         | incentivize racing towards the best solution as fast as
         | possible.
         | 
         | Depending on program goals, both approaches have their place.
         | However for projects like Artemis which tried to minimize R&D
         | cost and save time through component re-use, the latter
         | approach would clearly be better.
        
         | dr_orpheus wrote:
         | Yes, the theory of cost-plus contracts is good. It is a way of
         | saying "this is a new piece of technology with ill defined
         | requirements and we need help developing it along the way."
         | Theoretically, it allows for changes and adaptations in
         | developments of technology. This is all in theory though and
         | what proponents of cost-plus would say. It does suffer from
         | some of the issues you have mentioned above. I think there is a
         | time and a place for cost-plus but there is definitely move
         | towards more fixed price contracts in civil and defense.
         | 
         | Becoming somewhat more common now is a hybrid approach of cost-
         | plus/fixed. Contracts for development phases up to a certain
         | milestone are set up as a cost plus contract and then
         | production comes under a fixed price contract.
        
           | tomatotomato37 wrote:
           | I wonder if some of the risks of cost-plus could be mitigated
           | by associating it with industry average running costs rather
           | than a per-project basis. So contractors would get a yearly
           | payment with as long as they are making progress on a
           | project, but any changes to the project are 1-to-1 with
           | additional costs so there would be no benefit to either
           | aggressive cost cutting or sandbagging expenses. Maybe also
           | make it so profit would be rewarded at project completion in
           | proportion to the running costs of however long the project
           | took to prevent pointlessly lagging or rushing projects. Of
           | course there would also have to be bullshit like opportunity
           | cost compensation and shit because these companies are so
           | profit-driven as to crash a project meant for the public good
           | if it means more profit from interest on a 0.5% bank account
        
             | klodolph wrote:
             | Cost-plus is _supposed_ to be primarily for research and
             | development, where the costs are highly variable to begin
             | with.
        
         | gabereiser wrote:
         | This has been my experience as well through contracts with the
         | government.
         | 
         | To further this, there is also no incentive and funds to
         | modernize an already existing product. If it was written in
         | Java 6 using J2EE, it's going to continue to be that until it
         | dies.
         | 
         | Folks I worked with also didn't care to up skill or learn new
         | ways of doing things because the incentive wasn't there. Their
         | cost was fixed, their price was fixed, their profit was fixed.
         | They will do the bare minimum to satisfy the contract.
        
         | ChrisLomont wrote:
         | >It's disincentivizing cost reductions and incentivizing cost
         | increases.
         | 
         | Competetive bids drive costrs down. The alternative to cost
         | plus is? Not having fixed profit margins, in which case there
         | is still incentives to increase costs.
         | 
         | In both cases the limit to costing is competition and the
         | contracting side.
         | 
         | Another way to think of it is cost plus lowers costs by
         | lowering risk. If the company were on the hook for uncertainty
         | (which is the case on ANY project), then they would have to
         | price that into the original proposal, as would their
         | competitors, ensuring more costs to cover the risk.
         | 
         | By lowering risk to companies, it provides another avenue to
         | lower costs. This happens in lots of markets - look at cost
         | margins where there is volatility versus margins where there is
         | predictability.
        
           | downut wrote:
           | Wait till you find out about Red and Blue teams submitting
           | bids from the same corporation. I sure loved being a small
           | part of that.
        
           | edmundsauto wrote:
           | This only works if the bids represent the same work, at the
           | same quality, on the same delivery schedule, with the same
           | feedback pathways and the same risk mitigations.
           | 
           | In other words, it is the "spherical cow" of contracting.
        
             | ChrisLomont wrote:
             | >This only works if the bids represent the same work, at
             | the same quality, on the same delivery schedule, with the
             | same feedback pathways and the same risk mitigations.
             | 
             | Why would this possibly be true? Two groups can bid on the
             | same project with different tradeoffs. Projects are
             | complex, and there are zillions of tradeoffs to make a
             | competitive bid. The group offering the project then
             | evaluates the bids, often with multiple rounds of feedback.
             | 
             | And generally then these projects initially got to several
             | competitors, with fewer getting follow-on work, causing
             | them all to try really hard to deliver good work.
             | 
             | Future projects are always worth more than current
             | projects, so only an idiot does bad or over-cost work
             | often. Such groups eventually don't get more work.
             | 
             | I've worked on such bids for decades. Multiple groups bid,
             | with a statement of work. The other side evaluates the
             | bids. Cost plus simply allows groups, when bidding to not
             | have to use larger multipliers to mitigate risk, since some
             | of the risk goes to the offeror.
             | 
             | If you were running a company, and you had two ways to bid
             | a contract, firm fixed price vs cost plus, which do you
             | think provides less risk to you?
             | 
             | And how does a company account for risk?
             | 
             | Higher prices, end of story. This is simple economics.
             | 
             | It's why less risk results in smaller margins throughout
             | pretty much all industries. It allows stable planning.
        
               | ClumsyPilot wrote:
               | "And how does a company account for risk?
               | 
               | Higher prices, end of story. This is simple economics."
               | 
               | The job of the company is to manage risk of the project
               | they are delivering, and let the ones that do it well
               | win. What the hell is the point of private sector if the
               | taxpayer pics up the tab every time something goes wrong?
               | 
               | I don't know what bids you dealt with, the ones I did
               | looked nothing klike what you describe. For any non-
               | mundane work, that's not like, paving a street, you low-
               | ball the bid, deliver the bare minimum the paperwork
               | allows and then keep milking the government for
               | improvements because what you've delivered is not good
               | enough.
               | 
               | If the bid is about new technology, the tradeoffs cannot
               | be understood by non-experts, and are difficult to
               | pinpoint even for experts. The expertiese required to
               | access how good is the bid is the same as the expertiese
               | needed to design the system -> if you have that
               | expertiese on hand, you would not need to outsource the
               | design.
               | 
               | The process is insanely time intensive, expensive, and
               | difficult to navigate. Not because government is
               | inefficient, but because taht's the nature of new
               | technology.
               | 
               | > Future projects are always worth more than current
               | projects, so only an idiot does bad or over-cost work
               | often. Such groups eventually don't get more work.
               | 
               | In UK Capita get work again and again despite fucking it
               | up all the time
        
           | zbrozek wrote:
           | Cost plus isn't used just at NASA. It's even more evil in
           | other arenas, like electricity in California. Our regulators
           | allow for a fixed profit margin for opex and a higher fixed
           | profit margin for capex. This has the twin effects of running
           | things to failure (and igniting the state) in order to avoid
           | opex and instead claim capex, and also motivating as-high-as-
           | possible costs for everything. No competitive bids are
           | possible.
        
             | jiggawatts wrote:
             | The same madness happens here in Australia too. Just
             | recently I did an IT project for a local electric utility
             | company and they were blowing $200K on firewalls for a
             | system used by 10 people. Similarly they "upgraded" a
             | perfectly good 10 Gbps fixed line to 200 Gbps for the same
             | group of users. They can utilise maybe 1 Gbps on a busy
             | day.
             | 
             | They also get a fixed profit ratio relative to capex. So
             | they burn giant piles of money to get their percentage from
             | the government...
        
           | LegitShady wrote:
           | >The alternative to cost plus is?
           | 
           | Contracts where the contracting party agrees to a % of
           | responsibility. When the project runs over the profit is
           | reduced by the overrun * the percent responsibility.
           | 
           | Lets say the agreement has 25 million in profit and 40%
           | responsibility. If the project runs over by $2m, the
           | contractor eats $2m * .4 = $800k reduction in profit so now
           | it's $24.2m.
           | 
           | Then they're actually incentivized to not have overruns.
        
             | ChrisLomont wrote:
             | >Contracts where the contracting party agrees to a % of
             | responsibility.
             | 
             | Except no big agency does this because it's a legal
             | nightmare. The others (cost plus and firm fixed) are well
             | explored.
             | 
             | >Then they're actually incentivized to not have overruns.
             | 
             | Everyone has incentives not to overrun - it means you're
             | less likely to get future work, and future work is worth
             | much more than overrunning current work.
        
               | LegitShady wrote:
               | >Except no big agency does this because it's a legal
               | nightmare.
               | 
               | agencies are starting to do it more and more often. It
               | won't get explored if people are scared, but it will get
               | explored if people actually want to fix the problems with
               | procurement overruns.
               | 
               | >Everyone has incentives not to overrun
               | 
               | in cost plus your overrun often directly leads to you
               | making more money. So no, not exactly.
               | 
               | >it means you're less likely to get future work, and
               | future work is worth much more than overrunning current
               | work.
               | 
               | Maybe, maybe not. Lots of things have few competitive
               | bidders, or bidders who bid knowing they're going to make
               | overruns and claims to make the contract profitable when
               | their bid never was. it's often called 'buying the job'
               | in other industries.
        
         | efsavage wrote:
         | A better way to align incentives would be to have the bids
         | specify fixed profits and a value engineering process. You bid
         | $10m + $1m profit. The project baloons to a $20m project, you
         | still make $1m. The project meets it's goals with a $5m budget,
         | you get $1m and a percentage of the shortfall. It can still be
         | gamed, but to a much lesser degree.
         | 
         | I worked on a 9-figure construction project and there were two
         | full-time engineers specifically tasked with looking for ways
         | to _reduce_ the cost of the project, because it was essentially
         | free money for the contractor. These two people generated
         | millions in profit for the company.
         | 
         | https://www.fhwa.dot.gov/construction/cqit/vecp.cfm
        
           | bryanrasmussen wrote:
           | Good, but often people reduce costs by using lower quality
           | supplies so that isn't necessarily foolproof either.
        
           | Closi wrote:
           | All these approaches have plusses and minuses and their own
           | risks. The risks with the approach you have described are
           | that:
           | 
           | a) Unless very carefully managed, you can end up with
           | contractors being incentivised to cut corners (i.e. We make
           | more money if we buy the cheapest doors possible, regardless
           | of if they only last a few weeks).
           | 
           | b) If contractors have fixed profits at their bid-price, they
           | will have zero incentive to accept any change requests
           | (unless they come with additional margin, in which case,
           | overspends will magically turn into change requests).
        
             | airstrike wrote:
             | If those doors are still built-to-spec, then shouldn't you
             | be fine?
        
           | Retric wrote:
           | There are a lot of games you can play to make say rent look
           | like a cost on a contract while another entity makes a profit
           | from that rent. Worse you still have incentives to offload
           | costs onto a contract. For example someone finishes an
           | unrelated contract your might as well move them to a profit +
           | contract rather than benching them or immediately laying them
           | off.
           | 
           | In the end markets simply aren't efficient without pricing
           | information. If you can't get someone to bid a fixed price
           | you might as well keep in in house.
        
             | krapht wrote:
             | Those games you play are a lot easier to deal with
             | oversight-wise. I disagree with your conclusion. You're
             | assuming in-house doesn't have the same perverse
             | incentives. Also, pricing information can be impossible to
             | discover. You often hear on HN how nobody can realistically
             | estimate large software programs. Under that regime, what
             | good is a firm fixed price contract? What'll happen is that
             | the company, once it goes over-budget, will stop work
             | and/or go bankrupt depending on the legal contract it
             | signed. Then the client has no choice but to add more money
             | into the pot - which suddenly sounds like a cost+ contract.
        
               | Retric wrote:
               | I have worked on plenty of fixed price software projects.
               | The simple reality is when you fix costs quality becomes
               | the flexible metric, but meeting the minimum project
               | goals becomes really important. However, considering how
               | many software projects fail reaching the agreed upon
               | minimum at the agreed upon price is vastly better than
               | what generally happens.
               | 
               | As to failing to finish a project the wonders of fixed
               | price contracting is you can pay at completion of some
               | milestone. Of course that means people need to pad the
               | price even more ahead of time to assume that risk, but
               | price becomes a really useful signal.
        
         | photochemsyn wrote:
         | One of the areas where this seems to have happened is at the
         | NSA, which usually keeps its contracts very secret, but due to
         | William Binney's whistleblowing, it was revealed that the
         | inexpensive solution (ThinThread) was passed over in favor of
         | the expensive solution (TrailBlazer).
         | 
         | https://whistleblower.org/whistleblower-profiles/thinthread-...
         | 
         | Part of the problem here is that the government actors
         | selecting the contracts also want more money flowing through
         | their agency, and they seem to get kickbacks in the form of
         | 'retirement positions' with the very private contractors
         | they're directing contracts to.
        
         | avalys wrote:
         | This is why it's ridiculous that the US Affordable Care Act
         | (Obamacare) "caps" profit for health insurers as a fraction of
         | premiums collected. It provides a direct incentive for them to
         | increase healthcare costs, absolutely the opposite of what
         | government policy should be doing.
        
       | dbg31415 wrote:
       | For those of us who embrace agile methodologies... there is
       | always benefit to cost plus contracts.
       | 
       | Clients never have all the requirements up-front, and even if
       | they did requirements tend to shift as we plan, design, build,
       | test...
       | 
       | It's also nice to not have to go through a lengthy contract
       | negotiation for change orders.
       | 
       | Look, I hear the "lack of incentive" argument, but I think it's
       | less about trying to over-bill clients, and more about trying to
       | adapt to ever-changing needs of clients. Not sure "plague" is the
       | right term.
        
       | [deleted]
        
       | newaccount2021 wrote:
        
       | simulate-me wrote:
       | Companies receiving these contracts (either fixed-price or cost-
       | plus) will be incentivized to maximize profit and the expense of
       | the shareholder. I don't think it's possible to remove this
       | incentive. Instead, the government should be more careful with
       | whom receives the contracts. For instance, SpaceX seems dedicated
       | to doing a good job and driving costs down. Therefore, right now,
       | SpaceX should receive more contracts. SpaceX's focus may change
       | in the future, and it's the government's responsibility to pay
       | attention to those changes and change contractors if SpaceX
       | starts leeching off of government funds. Adequate competition for
       | contracts will align incentives more than the structure of any
       | particular contract. Everyone here saying that Lockheed turns a
       | 10B problem into 20B of work due to cost-plus might be correct.
       | But why can't the government find someone to do the work for 10B?
       | With proper competition, incentives will align.
        
       | aurizon wrote:
       | If one contrasts the bang for the buck between the 'usual NASA
       | suspects' and the performance of SpaceX, there is a lesson there.
       | In addition, the NASA Mil-SPEC process is rooted in a far past
       | era that insisted on x-rays of every resistor and part for making
       | sure nothing ever failed. This is the old For want of a nail...
       | https://en.wikipedia.org/wiki/For_Want_of_a_Nail Modern parts
       | manufacture now makes parts with 7 or higher 9's of reliability.
       | 6 nines = 1 in a million fails, so a spacecraft with a million
       | resistors is a 50:50 effort and so on. This hunt for more 9's has
       | led Nasa down a cost rabbit hole, exacerbated by these fees+
       | contracts. Of course, there are also overlays of accounting and
       | admin verification that can add 25-50% to a project, esp small
       | runs. On the other hand, we see mention of 60% of Russian weapons
       | fail in various ways in Ukraine - training, bad parts, ruble
       | theft. I have read stories that maintenance crews in Russian
       | warehouses have sold as many as 50% of the diesel engines as well
       | as gold plated circuit boards and edge connectors have been sold
       | by employees for scrap - as well as ruble diversions for
       | $600,000,000 Italian yachts - I think the SpaceX method is the
       | best.
        
       | ineedasername wrote:
       | Fixed price allows less flexibility if "gotchas" are found during
       | development, which they almost always are.
       | 
       | But you can get to a middle ground: A large project where I work
       | did fixed price but built in $X hours of additional work to the
       | price, to be used on a discretionary basis when unexpected issues
       | arise. More flexible than pure fixed-price and not as open-ended
       | as costs plus.
       | 
       | Still not perfect: the vendor has every incentive to utilize
       | every last $X hour in the pool, but strong oversight kept the
       | worst of that in check.
        
       | bluGill wrote:
       | I disagree. Cost-Plus might not be the right model, but fixed
       | price only works if all the risks are known and so easy to
       | account for.
       | 
       | Plenty of builders can make you a house on a fixed-cost. I used
       | to know one, and every spec house he built was within $1000 of
       | his initial price because he could look at prints and know in an
       | hour how much the lumber, labor, plumbing, electric, cabinets...
       | would cost. He could figure this out even if it was the first
       | time building that print. (spec house was important - if it was
       | custom the owners were use to add $30,000 in upgrades)
       | 
       | SpaceX can quote you a fixed price launch of crew dragon to ISS.
       | However if you want to build a new ship - there are too many
       | unknowns. I'm sure if NASA was content to stick with the
       | opportunity rover design they could have thousands on the surface
       | of mars by now for the budget that has gone into the various
       | programs we have done since then - but we learn a lot more from
       | the new programs that opportunity can't give (perhaps we would
       | know more about mars?).
       | 
       | Most of the things NASA does are things where the risk is far too
       | high for anyone sane to take on all the risk in a fixed price
       | contract. Instead NASA needs to take on the risk in some way.
       | Either that means some form of contract like cost-plus, or a lot
       | of smaller contracts such that everyone can succeed at their
       | contracts while the project itself is a failure (I'll make module
       | X exactly to specs, too bad if you mess up the specs). All forms
       | of such contracts are subject to abuse, NASA needs to figure out
       | how to manage that abuse.
        
         | dotnet00 wrote:
         | But isn't accounting for risks and having contingencies to
         | minimize their impact part of good engineering practice? Eg.
         | when designing a new rocket, you know that the engines might
         | have issues causing delays, you can't predict exactly what
         | issues but you can estimate how much extra money and time you
         | could lose there.
         | 
         | For instance, as part of their filing for the HLS competition,
         | SpaceX supposedly had around ~400 pages just discussing
         | cryogenic propellant storage and transfer, along with the
         | associated risks and how they would mitigate them.
         | 
         | It's also a bit of a stretch to say NASA isn't taking on risk
         | in fixed price, as they're still paying large sums of money for
         | each agreed upon milestone. The point is that the risk needs to
         | be shared. Cost+ takes away pretty much all of the risk for the
         | company, taking away their incentive to do their best
         | (especially considering that until SpaceX came around and blew
         | the doors open for smaller companies, there were only a handful
         | of competitors who were all basically the same culture wise).
        
         | lamontcg wrote:
         | Strict fixed-pricing seems like a recipe for something like
         | JWST to fail miserably in the future.
         | 
         | For an expensive one-off like that there needs to be wiggle
         | room to deal with design uncertainties and the unknown-
         | unknowns.
         | 
         | Fixed price might be more reasonable for smaller less expensive
         | missions where the uncertainties are less and the tolerance for
         | failure is higher.
        
         | trothamel wrote:
         | SpaceX did bid fixed-price for HLS, the moon lander they're
         | working on. That project will required developing refueling
         | from an on-orbit propellant depot to succeed.
         | 
         | The thing with SLS is it was supposed to be low-risk, based on
         | Space Shuttle heritage - it doesn't do much that's new. Despite
         | that, it's on a cost plus contract that's ballooned.
        
           | nickff wrote:
           | Nobody in their right minds would have touched SLS with a
           | fixed-price contract; NASA is too involved in the design,
           | construction, and testing.
        
           | masklinn wrote:
           | > The thing with SLS is it was supposed to be low-risk, based
           | on Space Shuttle heritage - it doesn't do much that's new.
           | 
           | HLV would have been a low-risk launcher based on the shuttle.
           | SLSs is a new launcher build from recycled parts.
        
           | sidewndr46 wrote:
           | Not just heritage, the SLS is basically what you get if you
           | move the Space Shuttle engines onto the propellant tank and
           | remove the orbiter vehicle. Then discard the reusability
           | requirement and you've got SLS.
           | 
           | In the process of this, everything is being modernized. This
           | is where all the cost comes from.
        
           | bluGill wrote:
           | SpaceX only did that is they wanted to do it anyway, so they
           | were willing for the risk
        
         | Closi wrote:
         | The counter-problem is that a cost-plus contract works the
         | opposite way - you are incentivised to account for none of the
         | risks in your initial bid to make your quote competitive, and
         | the sales strategy is to 'land and expand' (i.e. get the
         | initial contract and then expand it's value - sales teams will
         | openly talk about land and expand behind closed doors).
         | 
         | In practice this means that the quotes you get back are much
         | harder to assess from a commercial perspective, as you are
         | trying to weed out which companies are underquoting.
         | 
         | Also cost plus contracts almost always end up being cost 'plus
         | plus' if you dig enough under the covers in my experiences in
         | procurement/contract management (there are always hidden fees
         | and profit lines, and too many opportunities for conflicts of
         | interest or to charge more to the open book), so even a low %
         | can just mean more 'hidden' profits. You could write a book on
         | all the ways to extract additional profit from an open book
         | contract.
         | 
         | IMO the best model isn't an either/or approach, it's a mix of
         | models where the right model is used at the right time
         | (including open book, fixed price, rate cards, hybrid contracts
         | e.t.c.) where the contracts are adequately sized & scoped (i.e.
         | several small fixed price contracts with set deliverables which
         | have value on their own rather than one huge contract with one
         | massive deliverable at the end).
        
         | uberman wrote:
         | This 100% and it is not just super risky things like "exploring
         | space".
         | 
         | If you have ever PIed on a government contract you will know
         | that the program manager will almost certainly deviate from
         | what is in the contract. They will call unbudgeted out of town
         | meetings, ask for unbudgeted reporting, demand unbudgeted
         | changes to the deliverables.
         | 
         | As a contractor working with the government, "cost plus" is the
         | only sane option. The program manager is not going to have the
         | bandwidth to renegotiate (and bid out?) in the almost certain
         | event of a change in scope.
         | 
         | The alternative to "cost plus" is defensive billing where the
         | contractor attempts to devine and account for extra non-
         | contracted work. That lead us in the past to $1000 hammers and
         | no-one liked that either.
        
         | Aperocky wrote:
         | > stick with the opportunity rover design they could have
         | thousands on the surface of mars
         | 
         | Now that's something I'm not against.
        
         | gpm wrote:
         | NASA doesn't need to be in the business of managing that risk
         | and the abuse that comes with it. NASA can pay a fixed cost
         | equal to the expected cost of the project, and the contractor
         | can buy insurance if they want insurance against cost overruns.
         | 
         | Insurance companies are in a much better place to price this
         | insurance than NASA, because they have the correct financial
         | incentive to do so well, and no political incentives to do so
         | poorly.
        
           | NovemberWhiskey wrote:
           | > _Insurance companies are in a much better place to price
           | this insurance than NASA_
           | 
           | Is that really a thing? The risks of adverse selection and
           | moral hazards would seem insurmountable.
        
             | bluGill wrote:
             | You can get insurance on anything you want. However the
             | more unknowns there are, the more they will charge. You can
             | get fire insurance that will cover even if you burn your
             | house down - but it will cost you (not having insurance and
             | burning your house down might cost $.01 more than buying
             | insurance)
        
             | gpm wrote:
             | You can negotiate insurance for just about anything (there
             | are sometimes laws against things like taking out life
             | insurance policies against a third party, but none that
             | would apply here). No doubt the insurance company would
             | insist on various forms of audits, similar to what the
             | government insists of for cost plus contracts today.
             | Probably the most successful contractors wouldn't pay an
             | insurance company for this, because it's a stupid model for
             | contracts that wastes resources, but it wastes no more
             | resources than having the government play the role of the
             | insurance company.
        
               | teruakohatu wrote:
               | I think you need to articulate why you think the govt. is
               | forced into this insurer role. They are no different to
               | any large private buyer.
               | 
               | Any insurance would be expensive, and would be a cost
               | passed to the government, as any other project related
               | costs are. The insurance provider spreads risks across
               | policies but since all these policies would probably be
               | for government contracts, the costs would all be passed
               | on to government. The government would end up paying for
               | all the policies plus the insurance company profit
               | margin.
               | 
               | The only winner here is the insurance company, maybe the
               | contractors. The government will be slightly worse off.
        
               | bluGill wrote:
               | They don't have to, but someone will be the insurance
               | provider and the government will pay for it. The
               | government by playing insurance has better options to cut
               | a project if things are getting to expensive, but this
               | requires some willingness to cut project scope which they
               | might not be willing for (and a contract that allows such
               | a thing).
        
               | gpm wrote:
               | > I think you need to articulate why you think the govt.
               | is forced into this insurer role. They are no different
               | to any large private buyer.
               | 
               | An insurance provider is a party taking financial risk if
               | something goes bad for someone else. In the cost plus
               | contracting model, the government is taking the financial
               | risk if the project goes poorly for the contractor, that
               | is the government is providing insurance.
               | 
               | > The insurance provider spreads risks across policies
               | but since all these policies would probably be for
               | government contracts, the costs would all be passed on to
               | government.
               | 
               | Of course, there is no free money here. However the
               | government can correctly evaluate the costs of the
               | different proposals under a fixed cost contract model,
               | whereas they are not capable of correctly evaluating the
               | cost of the insurance that they add on top in a cost plus
               | model, because they aren't set up to correctly price the
               | insurance they are selling. This means that in the fixed
               | price model, they can get a much better approximation of
               | the cost in the value/cost equation they are trying to
               | maximize when evaluating bids, and it means that
               | contractors are motivated to provide options that
               | maximize the same, instead of being motivated to provide
               | options that maximize the difference between how the
               | government miss-prices the insurance, and the actual
               | value of the insurance. In the end everyone ends up
               | better off, because there is less waste.
        
               | NovemberWhiskey wrote:
               | I should probably have been clearer. I understand you can
               | insure all kinds of risks, and that you can ask an
               | underwriter to insure against most anything. My question
               | is more whether this is a well-formed insurance market
               | where coverage is available under economically realistic
               | terms.
        
               | gpm wrote:
               | I can't say that I'm aware of an active market for
               | insurance similar to this, not that I would necessarily
               | be aware of one.
               | 
               | If one doesn't exist, that should just be a sign that the
               | government really shouldn't be providing it either
               | though, because it isn't profitable. The government isn't
               | somehow better placed to insure R&D work (or whatever you
               | want to call the work being discussed) than any other
               | insurance company is.
        
               | bluGill wrote:
               | The government is better able to set a fixed budget
               | though. R&D as in do X hours of work on FTL is much
               | better than deliver FTL (I intentionally picked something
               | impossible - though in a the world R&D should be about
               | things you think are possible but are not sure of)
        
               | gpm wrote:
               | What you're describing isn't a cost plus contract, it's a
               | fixed cost contract for a study (assuming cost/hour is
               | fixed). These exist, they're frequently a good idea.
               | 
               | Cost plus would be "deliver a FTL ship, we'll pay you X *
               | costs, no it doesn't really matter if you go 10x over
               | what you initially quoted us for the work and still don't
               | have the thing". You can see why contractors under that
               | model are willing to make unrealistic quotes and promises
               | about FTL, or for a real world example why SLS is many
               | years and many billions of dollars behind schedule.
        
           | teruakohatu wrote:
           | > NASA can pay a fixed cost equal to the expected cost of the
           | project
           | 
           | Sure they can, but when they decide to tweak the project the
           | company can tell them "no, that sounds risky".
           | 
           | So what will happen is the contract will end up stating
           | something like all adjustments are priced at cost plus... and
           | NASA is back at square one.
        
             | gpm wrote:
             | You don't get to change the deliverables of cost plus
             | contracts without re-negotiation either. That's not the
             | risk that is being avoided here, the risk is that the
             | company is going to decide to ask for more money for the
             | same service they initially promised.
             | 
             | For example with Boeing's recent starliner tests, they
             | would be asking for more money to fly the orbital flight
             | test that they initially promised, because they fucked it
             | up the first time.
        
       | Symmetry wrote:
       | Fixed price contracts may cost the government a lot of time and
       | money but they might still be good insurance against political
       | risk. In WWI many companies that won armament fixed price
       | contracts were able to make large profits, partially leading to a
       | backlash in the interwar years over the idea that the US had been
       | led into WWI by corporate interests leading to US isolationism
       | before WWII. By using mostly cost plus contracts in WWII FDR was
       | able to diffuse the political issue.
       | 
       | I sort of worry that even if SpaceX is able to provide launch
       | services for NASA at a far lower rate than other companies, and
       | that even if their absolute profit s are lower than their
       | competitors they'll still have profit margins so high that it'll
       | lead to backlash given the weak competition.
        
       | bryanlarsen wrote:
       | Fixed price contracts are also similarly abused.
       | 
       | https://spacenews.com/nasa-inspector-general-criticizes-addi...
        
         | Robotbeat wrote:
         | But not as easily. Boeing has since had to eat the costs
         | associated with an extra test flight.
        
           | nickff wrote:
           | Fixed price has cost NASA dearly in the past, because NASA
           | often changes things after making a purchase decision. The
           | 'change orders' are often where contractors make their real
           | money.
        
           | NovemberWhiskey wrote:
           | Contractors may lose out on the initial fixed-price contract,
           | but they'll make it up on change requests - for any kind of
           | realistic scale, the customer never knows exactly what they
           | want, there are always changes, and by that point it's
           | largely unrealistic to shop those contracts elsewhere.
        
             | Robotbeat wrote:
             | Not in this case as commercial crew has two providers. So
             | if Boeing doesn't do the work, they just won't be paid, and
             | SpaceX will get more flights (and this is exactly what has
             | happened). If this keeps going indefinitely, NASA will on-
             | board a new partner besides Boeing, such as SNC's Dream
             | Chaser (other potential options include Blue Origin, who
             | eventually want to build an orbital crew vehicle, and even
             | technically Lockheed Martin who own the plans to Orion and
             | are allowed to bid it commercially).
        
               | NovemberWhiskey wrote:
               | I suppose it depends on the nature of the contract; for
               | launch services I guess that makes sense; but for a
               | development project, it's different - if you give
               | Lockheed Martin the contract to build the Mars Ascent
               | Vehicle, you're probably going to need to revise the
               | requirements through the lifetime of the project, and
               | it's not very credible to say "OK, Boeing's taking over
               | from here" for the change requests.
        
               | rozab wrote:
               | Commercial Crew _is_ a development project, I don 't see
               | what the difference is.
        
               | Robotbeat wrote:
               | Funny you say that because NASA is taking a very similar
               | approach to the HLS lander for Artemis. They did start
               | with just one provider (as Starship is the only one they
               | could afford) but they're trying to include a second
               | lander provider ASAP, partly by the insistence of
               | Congress (who doesn't like that their typical defense
               | contractor donors didn't get picked for the first HLS
               | lander).
        
       | rhacker wrote:
       | Let's say you're Lockheed and you have a 10B budget for X but you
       | have a contract that lets you go over. What's to stop you from
       | immediately placing 9B of that in rich pockets and trying to
       | build the damn thing for 1B. After all there's no incentive to
       | actually deliver for the 10B so asking for another 5B - bringing
       | the total actual effort to 2B (see what I did there).
        
         | zardo wrote:
         | > What's to stop you from immediately placing 9B of that in
         | rich pockets
         | 
         | The government accounting that goes along with the contract.
         | They can waste money or do a bad job, but they can't just say
         | they spent the money on executive bonuses.
        
         | tomrod wrote:
         | QA/acceptance requirements. But you are right that this game is
         | hard to play.
        
       ___________________________________________________________________
       (page generated 2022-05-04 23:00 UTC)